Dougs Third Go
I got it to about £2400
Peter, if you can do all that in 3.5 days and be happy with a day rate and do it properly, then can i have some of whatever you are smoking or snorting please....
I work on about 6m2 a day when working out a time scale for a job, so would be looking at 7 to 9 days on that job, without see it, from start to finish.
Peter, if you can do all that in 3.5 days and be happy with a day rate and do it properly, then can i have some of whatever you are smoking or snorting please....
I work on about 6m2 a day when working out a time scale for a job, so would be looking at 7 to 9 days on that job, without see it, from start to finish.
I'd love to be able to make a living doing 6m a day but unfortunately NI rates of £12-15pm wouldn't allow it and we need to get the finger out and be doing 15-20m a day. Couldn't imagine a morning of latexing and a 50m floor ever taking 9 days.
Well your going to get some poo now pal, taking off your own doors and re hanging them .I did not say i did 6 m2 a day, i said i work on 6 m2 a day for the over all job.
For the job posted.....
Day 1... Collect 25 bags of adhesive plus self leveling and grout if colour know. Stick down ufh and self level if floor is clean and primed, if not lift wires and do properly. Clean floor of contamination ( plaster etc.) vac and prime.
Day 2.... Finish of what was completed from day 1. Remove doors, cut door stops etc., set out and load out some tiles, adhesive.
Days 3,4,5,6... Tile floor, flat level and lip free, with the planks tiles supplied, 12 m2 per day. Do sample grout colours for customer to make there choice.
Day 7....clean and grout floor.
Day 8... Re hang doors, clean floor and silicon around and tile to skirting and kitchen unit where cracks will appear and to give expansion for floor.
As i said, its all about the finished job and service given.
Andy i do start clearing up for the day at 3:30 to leave about 4. Nice to have a home life as well.